Lucara Diamond Corp. has reported significant progress on its Karowe Underground Project (UGP), with underground lateral development advancing by 466 metres during the third quarter of 2026 as the company moves closer to transitioning the project into full-scale production.
In its Q3 2026 results, Lucara revealed that the project transitioned from shaft construction to underground lateral development during the quarter, marking an important milestone in the development of the underground mine.
The production shaft was handed over to the owner’s team in August 2026, while development waste hoisting commenced following the Botswana Department of Mines’ licensing of the rock winder.
Mining contractor Group R Mining also commenced underground lateral development, advancing 466 metres during the reporting period.
Lucara invested US$40.7 million in the project during the third quarter.
As at September 30, 2026, the remaining cost to complete the project, including contingency, stood at US$245.2 million, with a further US$92.9 million in committed costs not yet incurred.
The total estimated cost of completing the underground project is US$779.2 million, including contingency, with full-scale production anticipated in the first half of 2028.
The underground development is designed to access the highest-value portions of the Karowe orebody, with initial planned underground diamond production expected to come predominantly from the EM/PK(S)4 geological unit.
Once operational, the underground project is expected to extend the life of the Karowe Mine to 2038, supporting the continued production of high-value diamonds and extending the mine’s contribution to Botswana’s diamond industry.
The project represents a major investment in the long-term future of the Karowe Mine as Lucara progresses towards unlocking deeper sections of the orebody.